JSW Steel to expand its Salem steel plant

JSW Steel is planning to increase the steel making capacity of its Salem Steel plant in Tamil Nadu with investment of Rs. 10,000 million. The company makes various kinds of automotive steels and high speed rails which it exports to other countries. The company which uses the private Marg Port in Cuddalore for its import needs of 1.0 million tonne of coking coal and 1.5 million tonne of iron ore is in talks to buy the Cuddalore port. The project will increase steel making capacity from 1.0 mtpa to 1.30 mtpa. The project also will increase the capacity of coal based captive power plant from 67 MW to 97 MW.

The project involves setting up of a sinter plant of 90 cu.meter, a energy optimizing furnace (45 to 65 T), continuous casting machine of 0.45 mtpa , air separation plant of 250 tpd, captive power plant of 30 MW. The project cost is estimated at Rs. 10250 million.

 
Sl.NoManufacturing FacilitiesCapacity (in million TPA)Current Status
1.Sinter Plant – 3 (90 m2)1.06Construction Yet to start
2.BF – 1 (402 to 650 m3)0.316Construction Yet to start
3.BF – 2 (550 to 650 m3)0.105March 2019
4.EOF – 1 (45 T to 65 T)0.23March 2019
5.Ladle Furnace – 1 with Common
VD (45 T to 65 T)
20 T/heatMarch 2019
6.Continuous Casting Machine – 30.45March 2019
7.Bar & Rod Mill Augmentation0.08Construction Yet to start
8.Blooming Mill Augmentation0.12Construction Yet to start
9.Pickling and Annealing Steel unit0.06March 2019
10.Peeled and Ground Rods0.04Construction Yet to start
11.ASP 3 – 250 Ton/Day250 TPDConstruction Yet to start
12.Captive Power Plant30 MWDecember 2018