Bharat Petroleum Corp Ltd is setting up a LPG bottling plant near Madurai in Tamil Nadu. The project involves setting up of facilities for LPG bottling with a annual capacity of 45 metric tonnes, around 12,000 cylinders per day. The project cost is estimated at ₹ 800 million. The plant would serve districts like Dindigul, Madurai, Virudhunagar, Sivagangai and Ramanathapuram.
As of July 2020, the project is nearing completion. The company has 416 domestic LPG distributorships and seven in Puducherry supplying 1,22,000 cylinders per day.
Project Location | Madurai,Tamil Nadu |
Project Cost (in million) | ₹800 |
Project Capacity | 45 tpd |
Project Status | Implementation |
Commissioning Date |